Friday, July 13, 2012

Notice of road closures

Last Updated on Aug. 3rd:

The seal coating portion of this project is now complete.  The only remaining work to be performed is the striping of the pedestrian crosswalks, which will not require any street closures or parking inconveniences.   Thank you for your cooperation.

Work Day 4 was been cancelled due to threat of rain and was eventually completed on Monday, July 30th.  The tentative schedule for Work Days 5 & 6 is shown below.

Update, July 17th: plan for Work Day 2 revised and Work Day 6 added to schedule.

The Central Park Master Association is having seal coating applied to the asphalt road surfaces of North, East, South and West Central Park Avenues during the week of July 16, 2012.  Sections of these roads and their intersections will be closed while the work is performed. Residents of the Gardens and Meadows whose driveway enters those roads will have to move their vehicles on the day the seal coating is applied in front of their house.  On certain days the Van Dyke entrance to Central Park will be closed and on other days, the 22 Mile Rd. entrance will be closed. It will take six Work Days to complete this project.

Here is the full project plan along with an updated map, scheduled Work Days and locations of the road closures. A hard copy of the original plan was delivered to each home prior to Monday, July 16th.

If rain is forecast, the contractor will cancel that Work Day and move it to the next scheduled date, with the remaining schedule delayed accordingly. Below is the latest  Work Day schedule, which was revised to add Work Day 6 (to do the northerly portion of what had been planned for Work Day 2; the eastern portion of Work Day 6 has been reassigned to Work Day 5 - view the updated map by clicking here).

This is the latest Project Plan schedule.
  • Work Day 1 was completed on Monday, July 16, 2012.
  • Work Day 2 was completed on Friday, July 20th
  • Work Day 3 was completed on Wednesday, July 25th
  • Work Day 4 was completed on Monday, July 30th - everyone must enter and leave via Van Dyke
  • No seal coat work planned for Tuesday to avoid interference with the trash collection. 
  • Work Day 5 was completed on Wednesday, August 1st - everyone must enter and leave via 22 Mile Rd.
  • Work Day 6 was completed on Thursday, August 2nd.

If you have a question about this project, please put it in the comments below and it will be answered in the comments as soon as possible.  That way others who may have the same question can benefit, too.  If you would rather ask your question via e-mail, send it to "mike (at) grobbel (dot) org".