Most of the roadways at the Manors never received their top layer of
asphalt paving because of the developer's bankruptcy in 2007.
The
Manors co-owners voted earlier this year to approve a special
assessment to pay for the paving of the final layer on our streets and
access drives.
Our contractor has confirmed that
they will be doing the paving on Friday, Nov. 9, 2012. The contractor will be laying down 910 tons of
asphalt, which means that there will be a lot of heavy trucks coming in
and out that day.
Our affected residents will not be able to
enter or leave the
Manors with their vehicles during the hours of 7:00 AM through 7:00 PM on the day of
paving. Therefore, they will have to park along North Central Park,
West Broadway and other
nearby streets during that time period.
Please bear with us as we complete this important project.
Mike Grobbel
President - Board of Directors, Manors at Central Park Condo Association
http://manorsatcentralpark.blogspot.com
Monday, November 5, 2012
Saturday, October 6, 2012
Packard Proving Grounds Open House
The Packard Proving Grounds is holding an Open House on Sunday,
October 21, 2012. This is a rain or shine event and starts at 1:00 PM –
wrapping up at 5:00 PM. Admission is FREE.
Packards and other collector cars will be on display. The Open House will include food service, activities for the kids, and a chance to tour the buildings. Also, the Johnny Trudell Band will be playing their big-band sounds.
Packards and other collector cars will be on display. The Open House will include food service, activities for the kids, and a chance to tour the buildings. Also, the Johnny Trudell Band will be playing their big-band sounds.
Labels:
events
Sunday, September 30, 2012
Crosswalk Striping
The pedestrian crosswalk striping work will take place during the coming
week of Oct. 1 (weather permitting). Please be prepared to make temporary detours while the striping paint dries. These marked crosswalks will be
located at both entrances to Central Park and at various points along
the Central Park ring road. This work is the final phase of the asphalt
seal-coating project that began in July.
Residents are reminded that, by law:
a) vehicular traffic shall yield the right-of-way to pedestrians and bicyclists lawfully within an intersection or crosswalk
b) pedestrians may not walk in the roadway if there are sidewalks present. If there are no sidewalks, they must walk on the left side, facing traffic.
Furthermore, the speed limit is 25 MPH on all roadways within the Central Park planned unit development . If you are driving faster than that, you may not be able to stop in time if you come to a crosswalk with a pedestrian already in it. We have already had one child hit by a car this year while within a crosswalk and we do not need to have a repeat.
Even though these are all private roads within the Central Park planned unit development, the Board of Directors has the ability to ask the Shelby Township Police Department to enforce our speed limits and traffic control devices. Given the almost blatant disregard some of our residents display for the 25 MPH speed limit and our STOP signs, expect to see a lot of flashing blue and red lights around here in the very near future - just don't let them be seen flashing in your rear view mirror!
Residents are reminded that, by law:
a) vehicular traffic shall yield the right-of-way to pedestrians and bicyclists lawfully within an intersection or crosswalk
b) pedestrians may not walk in the roadway if there are sidewalks present. If there are no sidewalks, they must walk on the left side, facing traffic.
Furthermore, the speed limit is 25 MPH on all roadways within the Central Park planned unit development . If you are driving faster than that, you may not be able to stop in time if you come to a crosswalk with a pedestrian already in it. We have already had one child hit by a car this year while within a crosswalk and we do not need to have a repeat.
Even though these are all private roads within the Central Park planned unit development, the Board of Directors has the ability to ask the Shelby Township Police Department to enforce our speed limits and traffic control devices. Given the almost blatant disregard some of our residents display for the 25 MPH speed limit and our STOP signs, expect to see a lot of flashing blue and red lights around here in the very near future - just don't let them be seen flashing in your rear view mirror!
Labels:
maintenance,
roads,
traffic
Friday, September 21, 2012
Sept. 12, 2012 CPMA BoD Minutes
Central Park Master Association
Board of Directors Meeting Minutes
Sept. 10, 2012
Board of Directors Meeting Minutes
Sept. 10, 2012
APPROVED
- Meeting was called to order at 7:15 PM; Quorum established; present: Mike Grobbel, Mike Malone, Brian Pesola; excused: Ted McCoy; Ryan Dorner, Kramer-Triad was also in attendance.
- The Board approved the Minutes of the
- Sept. 12, 2011 Board Meeting
- Oct. 24, 2011 Board meeting
- Old Business
- Streetlight maintenance update - Ryan Dorner indicated that maintenance workers had completed work on the inoperative streetlights and that they were all operative again. One entire circuit of streetlights was found to be inoperative because someone had sprayed insecticide into the circuit breaker enclosure to kill wasps and the wet insecticide had short-circuited and “fried” the circuit breaker, which had to be replaced. Four other streetlights were found to have had the bulbs removed from them. The Board has reason to believe that these streetlights are being deliberately sabotaged by one or more Central Park residents and this issue will be mentioned in the forthcoming newsletter. Ryan Dorner will provide the Board with an estimated cost for repairing a typical streetlight outage so we can include it in the newsletter.
- newsletter communications to homeowners – Brian P. has begun drafting a newsletter and will send it out to the other Board members within the next few days; the Board discussed additional items to be included in the draft newsletter and also decided that the first newsletter will be mailed to all residents with a notice in it that future newsletters will be posted on the Central Park blog at http://centralparkassociations.blogspot.com to save an estimated $400 per mailing
- Owens Tree Service quote - Mike G. updated the Board regarding the tree trimming work to be performed by Owens per the recent quote we received; Ryan Dorner will contact Jim F. at Owens to get an estimated completion date
- MCI quote for fountains in the detention ponds
i.
fountain(s)
purchase costs – have received unit costs from MCI
ii.
electrical
installation costs – Ryan Dorner will contact Chuck Swan at MCI to see if they
have completed the estimate for providing electrical service to ponds number 2
(central), 3 (south) and 6 (north)
iii.
costs
to winterize and re-install in the spring - Ryan Dorner will contact Chuck Swan
at MCI to obtain an approximate annual cost for this recurring service
iv.
cost
estimates are needed in time for the next Board Meeting so that they can be
factored into the 2013 Budget discussion
- Asphalt seal coating and crosswalk striping – Board members report favorable feedback from residents, despite the weather delays; pedestrian crosswalk striping is tentatively scheduled for this coming Thursday, Sept. 13, 2012 (weather permitting); Brandon A. at Midwest Paving is still investigating the appearance issue noted on the Day 6 seal coat work.
- Spring Clean-up event held on April 28th feedback discussion; 55 bags of trash were collected by 14 volunteers; in 2013 the Board will need to promote this event better and contact Rizzo to have a 30 yard roll-off container dropped off in advance.
- New Business
- Groundwater contamination update - Mike G. provided an update to the Board; preliminary results of all irrigation well water testing within Central Park indicates no traces of VOCs such as TCE and TCA
- 2013 Annual Budget process timing; Brian P. will have a first draft of the proposed 2013 Budget available for discussion at the next Board Meeting
- Installation of new traffic signage
i.
add
two more "STOP" signs at the intersection of NCP and ECP to make it a
3-way stop intersection – the Board approved the installation of two more
“STOP” signs at this intersection; Ryan
Dorner to initiate the work order.
ii.
Add
"Pedestrian Crossing Ahead" signs either side of crosswalk near WCP
and St. Nicholas – the Board decided against installing warning signs based on
the fact that if we did it here, by extension we would have to do it at all
other crosswalks; the Board feels that the recent sidewalk alignment
improvements and upcoming pedestrian crosswalk striping will have brought all
pedestrian crosswalks to the same level of safety and visibility
- Snow and Lawn contracts – the Board voted to award the following contracts to True North:
i.
A
three-year Snow Removal contract for an annual amount not to exceed $14,500;
expires April 2015
ii.
A
three-year Lawn Maintenance contract for an annual amount not to exceed
$19,365; expires November 2015
- The next Board Meeting will be held on Monday, Oct. 15, 2012 at 7:00 PM at Mike Grobbel’s condominium.
- The Meeting adjourned at 9:15 PM
Approved Minutes of all previous CPMA Board of Director meetings can be found on this web page.
Labels:
Master Association,
Minutes
Wednesday, September 12, 2012
Construction equipment south of Genisys Credit Union
You may have noticed the construction equipment that has recently been
moved onto the vacant parcel on Van Dyke south of the Genisys Credit
Union. I have learned that this vacant parcel is being used as a
staging site for the equipment and materials that will be used to
construct the new sanitary sewer that will be installed along the west
side of Van Dyke from 22 Mile Road south to a point about 1,000 feet
past 21 Mile Road (approximately here). The sewer project is expected to take six months to
complete. More information about the sewer project can be found in this article from the July 28, 2012 edition of the Source & Advisor.
Labels:
rumor mill,
township,
traffic
Friday, July 13, 2012
Notice of road closures
Last Updated on Aug. 3rd:
The seal coating portion of this project is now complete. The only remaining work to be performed is the striping of the pedestrian crosswalks, which will not require any street closures or parking inconveniences. Thank you for your cooperation.
Work Day 4 was been cancelled due to threat of rain and was eventually completed on Monday, July 30th. The tentative schedule for Work Days 5 & 6 is shown below.
Update, July 17th: plan for Work Day 2 revised and Work Day 6 added to schedule.
The seal coating portion of this project is now complete. The only remaining work to be performed is the striping of the pedestrian crosswalks, which will not require any street closures or parking inconveniences. Thank you for your cooperation.
Work Day 4 was been cancelled due to threat of rain and was eventually completed on Monday, July 30th. The tentative schedule for Work Days 5 & 6 is shown below.
Update, July 17th: plan for Work Day 2 revised and Work Day 6 added to schedule.
The Central Park Master Association is having seal coating applied to the asphalt road surfaces of North, East, South and West Central Park Avenues during the week of July 16, 2012. Sections of these roads and their intersections will be closed while the work is performed. Residents of the Gardens and Meadows whose driveway enters those roads will have to move their vehicles on the day the seal coating is applied in front of their house. On certain days the Van Dyke entrance to Central Park will be closed and on other days, the 22 Mile Rd. entrance will be closed. It will take six Work Days to complete this project.
Here is the full project plan along with an updated map, scheduled Work Days and locations of the road closures. A hard copy of the original plan was delivered to each home prior to Monday, July 16th.
If rain is forecast, the contractor will cancel that Work Day and move it to the next scheduled date, with the remaining schedule delayed accordingly. Below is the latest Work Day schedule, which was revised to add Work Day 6 (to do the northerly portion of what had been planned for Work Day 2; the eastern portion of Work Day 6 has been reassigned to Work Day 5 - view the updated map by clicking here).
This is the latest Project Plan schedule.
- Work Day 1 was completed on Monday, July 16, 2012.
- Work Day 2 was completed on Friday, July 20th
- Work Day 3 was completed on Wednesday, July 25th
- Work Day 4 was completed on Monday, July 30th - everyone must enter and leave via Van Dyke
- No seal coat work planned for Tuesday to avoid interference with the trash collection.
- Work Day 5 was completed on Wednesday, August 1st - everyone must enter and leave via 22 Mile Rd.
- Work Day 6 was completed on Thursday, August 2nd.
If you have a question about this project, please put it in the comments below and it will be answered in the comments as soon as possible. That way others who may have the same question can benefit, too. If you would rather ask your question via e-mail, send it to "mike (at) grobbel (dot) org".
Labels:
closures,
maintenance,
Master Association,
parking,
roads
Friday, May 11, 2012
Visteon demolition update thru May 10. 2012
UPDATED:
Click here for photos showing the demolition progress through July 12, 2012, along with the most recent air monitoring report.
Columbia Technologies continues to perform underground soil mapping for the Ford Motor Company on the vacant parcel to the north of the Manors and Kensington condos.
Click here for photos showing the demolition progress through July 12, 2012, along with the most recent air monitoring report.
Columbia Technologies continues to perform underground soil mapping for the Ford Motor Company on the vacant parcel to the north of the Manors and Kensington condos.
Labels:
Visteon
Subscribe to: