UPDATE: Mike Malone and Matt Karrandja will represent the Meadows and
Gardens, respectively, on the Central Park Master Association's Board of
Directors during 2014 and 2015. Click here for the names and contact information of all four current Board members.
The 2014 Annual Membership Meeting of the Central Park Master
Association will be held on Friday May 2, 2014 at the Shelby Twp.
Municipal Building. Sign-in begins at 6:30 PM and the meeting will
start at 7:00 PM.
The purpose of this meeting is to elect one representative each from the
Gardens and Meadows Associations to the Central Park Master Association Board of Directors. Only the homeowners in the Gardens and Meadows can nominate candidates to
represent them on the CP Master Board of Directors. However, all owners who live in the Manors, Kensington, Gardens and Meadows
Associations have the right to vote to select the Gardens and Meadows
representatives from among those who have been nominated.
If you are unable to attend, please fill out the
General Proxy you recently received in the mail and return it to either
Kramer-Triad or give it to a neighbor who will be attending so that we
can use your proxy to count towards making the
quorum. Click here to download and print a blank General Proxy form.
Click here to read the unapproved minutes of the 2013 Annual Membership Meeting.
Showing posts with label Minutes. Show all posts
Showing posts with label Minutes. Show all posts
Monday, April 28, 2014
Wednesday, March 27, 2013
Minutes of the March 25, 2013 BoD Meeting
Central Park Master Association
Board of Directors Meeting Minutes
March 25, 2013
(unapproved)
- Meeting was called to order at 7:02 PM; a quorum of members was present: Mike Grobbel, Mike Malone and Brian Pesola. Ted McCoy was absent. Also in attendance was Ryan Dorner of Kramer-Triad.
- The Board approved the Minutes
of the Oct. 15, 2012 Board Meeting as presented.
- Old Business
- Damaged streetlight replacement at Heyward and Kingsland: underground wires were also damaged and must be repaired after the frost is out of the ground; wire repairs and streetlight replacement will be made as soon as the weather warms up.
- Status of fountain installations in the three detention ponds: the Board approved and signed a contract providing for (a) the necessary electrical work to be performed by RB & Sons Electrical Contractor ($6,610) and (b) the purchase and installation of three Aquamaster brand, Master series ½ HP fountains with Lakewood spray nozzle by MCI Aquatic Management Co. ($9,300); expectation is that all work is to be completed before the start of Summer.
- Groundwater contamination
update by Mike Grobbel: “Step 1 Summary Report, Oct. 17, 2012” was
received on Jan. 15, 2013 from Dragun & Associates. This report
contains test results of groundwater samples taken from temporary
monitoring wells located just inside the eastern property line of the
former Visteon plant. These
monitoring locations were drilled at 13 different locations along the
property line extending from the northwest corner of the Manors at Central
Park north towards 23 Mile Rd. Testing of the groundwater from these 13
locations indicate only 3 locations where groundwater was found to be
contaminated by amounts of TCE in excess of the EPA drinking water
standard of 5 parts per billion.
These 3 locations are in an area that is between 850 and 1,100
feet south of the center line of 23 Mile Rd. and the water samples
were obtained at a depth of about 25 ft. below ground level. These TCE levels and the location where
the samples were obtained are just west of the area where similar TCE
levels were measured in April 2012 on the adjacent property that is owned
by Grand/Sakwa.
Labels:
Board of Directors,
groundwater,
Minutes
Friday, September 21, 2012
Sept. 12, 2012 CPMA BoD Minutes
Central Park Master Association
Board of Directors Meeting Minutes
Sept. 10, 2012
Board of Directors Meeting Minutes
Sept. 10, 2012
APPROVED
- Meeting was called to order at 7:15 PM; Quorum established; present: Mike Grobbel, Mike Malone, Brian Pesola; excused: Ted McCoy; Ryan Dorner, Kramer-Triad was also in attendance.
- The Board approved the Minutes of the
- Sept. 12, 2011 Board Meeting
- Oct. 24, 2011 Board meeting
- Old Business
- Streetlight maintenance update - Ryan Dorner indicated that maintenance workers had completed work on the inoperative streetlights and that they were all operative again. One entire circuit of streetlights was found to be inoperative because someone had sprayed insecticide into the circuit breaker enclosure to kill wasps and the wet insecticide had short-circuited and “fried” the circuit breaker, which had to be replaced. Four other streetlights were found to have had the bulbs removed from them. The Board has reason to believe that these streetlights are being deliberately sabotaged by one or more Central Park residents and this issue will be mentioned in the forthcoming newsletter. Ryan Dorner will provide the Board with an estimated cost for repairing a typical streetlight outage so we can include it in the newsletter.
- newsletter communications to homeowners – Brian P. has begun drafting a newsletter and will send it out to the other Board members within the next few days; the Board discussed additional items to be included in the draft newsletter and also decided that the first newsletter will be mailed to all residents with a notice in it that future newsletters will be posted on the Central Park blog at http://centralparkassociations.blogspot.com to save an estimated $400 per mailing
- Owens Tree Service quote - Mike G. updated the Board regarding the tree trimming work to be performed by Owens per the recent quote we received; Ryan Dorner will contact Jim F. at Owens to get an estimated completion date
- MCI quote for fountains in the detention ponds
i.
fountain(s)
purchase costs – have received unit costs from MCI
ii.
electrical
installation costs – Ryan Dorner will contact Chuck Swan at MCI to see if they
have completed the estimate for providing electrical service to ponds number 2
(central), 3 (south) and 6 (north)
iii.
costs
to winterize and re-install in the spring - Ryan Dorner will contact Chuck Swan
at MCI to obtain an approximate annual cost for this recurring service
iv.
cost
estimates are needed in time for the next Board Meeting so that they can be
factored into the 2013 Budget discussion
- Asphalt seal coating and crosswalk striping – Board members report favorable feedback from residents, despite the weather delays; pedestrian crosswalk striping is tentatively scheduled for this coming Thursday, Sept. 13, 2012 (weather permitting); Brandon A. at Midwest Paving is still investigating the appearance issue noted on the Day 6 seal coat work.
- Spring Clean-up event held on April 28th feedback discussion; 55 bags of trash were collected by 14 volunteers; in 2013 the Board will need to promote this event better and contact Rizzo to have a 30 yard roll-off container dropped off in advance.
- New Business
- Groundwater contamination update - Mike G. provided an update to the Board; preliminary results of all irrigation well water testing within Central Park indicates no traces of VOCs such as TCE and TCA
- 2013 Annual Budget process timing; Brian P. will have a first draft of the proposed 2013 Budget available for discussion at the next Board Meeting
- Installation of new traffic signage
i.
add
two more "STOP" signs at the intersection of NCP and ECP to make it a
3-way stop intersection – the Board approved the installation of two more
“STOP” signs at this intersection; Ryan
Dorner to initiate the work order.
ii.
Add
"Pedestrian Crossing Ahead" signs either side of crosswalk near WCP
and St. Nicholas – the Board decided against installing warning signs based on
the fact that if we did it here, by extension we would have to do it at all
other crosswalks; the Board feels that the recent sidewalk alignment
improvements and upcoming pedestrian crosswalk striping will have brought all
pedestrian crosswalks to the same level of safety and visibility
- Snow and Lawn contracts – the Board voted to award the following contracts to True North:
i.
A
three-year Snow Removal contract for an annual amount not to exceed $14,500;
expires April 2015
ii.
A
three-year Lawn Maintenance contract for an annual amount not to exceed
$19,365; expires November 2015
- The next Board Meeting will be held on Monday, Oct. 15, 2012 at 7:00 PM at Mike Grobbel’s condominium.
- The Meeting adjourned at 9:15 PM